Tall oven housing

Oven at hand height: dividers, appliance support and two doors.

Example 600 × 2070 × 560 mm - the same order applies to every width.

Tall oven housing: assembly instructions

  1. 1

    Before you start

    Lay cardboard or a blanket on the floor so the panels don't get scratched. Check against the list that you have every panel - labels match the stickers and the cutting list - and all the hardware. The edge-banded edge is the front: always face it forward.

  2. 2

    Left side and bottom

    Stand the left side on its edge, drilled face inwards. The bottom sits BETWEEN the sides, flush with the lower and front edge of the side (P1 and P2). Drive 3 confirmat screws through the holes in the side - middle one first, then the ends. Don't fully tighten until the carcass is assembled.

  3. 3

    Top panel

    The top panel P3 goes between the sides, flush with the top edge - like the bottom, only at the top. They join the left side with 3 confirmat screws.

  4. 4

    Dividers and fixed shelves

    The inner panels (P4, P5 and P7) go at the heights from the cutting list - they carry the appliance, so don't move them by a millimetre. Each joins the left side like the bottom: 7 confirmat screws.

  5. 5

    Right side closes the carcass

    Lower the right side P1 onto the free ends of the panels already fixed in the left side. Drive 13 confirmat screws through the right side, and only now tighten every confirmat fully.

  6. 6

    Diagonals and back panel

    Lay the carcass face down and measure both diagonals - they must match within 1 mm. Only then place the back panel P8 and P9 smooth face in, 2 mm in from the edges, and pin or staple it every 8-10 cm into the sides, bottom and rails (about 45). Once the back is on, the carcass can't rack.

  7. 7

    Legs

    Lay the carcass on its back and fix 4 legs to the bottom, 4-5 cm from the edges. Set them to plinth height (100 mm) - final levelling is done with a spirit level once the cabinet is in place.

  8. 8

    Oven

    The oven goes in only when the cabinet is in place and power is connected: slide it into the niche onto its support and fix it with 2-4 screws through the frame into the sides. Leave the air gap behind and below it.

  9. 9

    Hinges and doors

    Press the hinges (4 pcs) into the Ø35 cups in the doors and fix each with two screws. Screw the plates to the side at the same height as the hinges. Clip the doors onto the plates.

  10. 10

    Handles

    Fix the handles (2) with M4 screws through the front from inside. Drill with a template and a scrap board behind the front so the face doesn't chip.

  11. 11

    Adjustment

    Adjust the fronts: 3-4 mm gaps, edges in line with the neighbours. A hinge has three screws - side, height and depth.

  12. 12

    Plinth

    The plinth clips onto the legs - last, once the whole kitchen is in place and levelled.

The instructions are made by the same program that makes the cutting list - panels carry the same labels (P1, P2…) and the same number of screws and hinges as the hardware list.

Design your kitchen

With an order you get a cutting list with the same labels and a PDF guide for the whole kitchen.

Design your kitchen